ROAD SAFETY TREATMENT WORKS — TOODYAY ROAD
666. Hon ALANNA CLOHESY to the
parliamentary secretary representing the Minister for Transport:
I refer to the minister's recent media statement regarding
the wheatbelt highway review.
(1) What ''extensive
road safety treatment works'' are currently being carried out on Toodyay
Road in the wheatbelt region, what is the cost and when are they expected to be
completed?
(2) What road
treatment works were carried out on Toodyay Road in the wheatbelt region in
2014–15, what was the cost and when were they completed?
(3) What road
treatment works are planned on Toodyay Road in the wheatbelt region in 2015–16,
what is the budget and what is the expected completion date?
666. Hon ALANNA CLOHESY to the
parliamentary secretary representing the Minister for Transport:
I refer to the minister's recent media statement regarding
the wheatbelt highway review.
(1) What ''extensive
road safety treatment works'' are currently being carried out on Toodyay
Road in the wheatbelt region, what is the cost and when are they expected to be
completed?
(2) What road
treatment works were carried out on Toodyay Road in the wheatbelt region in
2014–15, what was the cost and when were they completed?
(3) What road
treatment works are planned on Toodyay Road in the wheatbelt region in 2015–16,
what is the budget and what is the expected completion date?
AnswerView source ↗
I thank the honourable member for some notice of the
question.
(1)–(2)
Construction of the left-turn pocket at Dryandra Road, costing $355 000, is
expected to be completed by June 2015.
(3) There are
development funds of $250 000 for intersection improvements at Morangup Road.
Construction funding will be requested for 2016–17 to complete the
works. There are development funds of $150 000 to commence design for seal
widening and clear zone improvements on Toodyay Road in the wheatbelt region,
with the intention of having some sections ready for construction in 2016–17.
question.
(1)–(2)
Construction of the left-turn pocket at Dryandra Road, costing $355 000, is
expected to be completed by June 2015.
(3) There are
development funds of $250 000 for intersection improvements at Morangup Road.
Construction funding will be requested for 2016–17 to complete the
works. There are development funds of $150 000 to commence design for seal
widening and clear zone improvements on Toodyay Road in the wheatbelt region,
with the intention of having some sections ready for construction in 2016–17.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.