❓ Hon. Amber-Jade Sanderson asks about the timeframe, responsible department, notification status, reason for lack of notification (if applicable), and estimated cost for power infrastructure upgrades at Morley Senior High School. The Department of Finance provides a timeline and identifies the managing department.
AnsweredQoN 1045Legislative Council
QuestionView source ↗
MORLEY SENIOR HIGH SCHOOL — AIR
CONDITIONING
1045. Hon AMBER-JADE SANDERSON to the
Leader of the House representing the Minister for Finance:
I
refer to question without notice 1026 and the Minister for Education's
advice that the Department of Finance has completed its validation for the
scope of work to provide power infrastructure upgrades to Morley Senior High
School.
(1) What is the time frame for
completed works?
(2) Which department is overseeing
the works?
(3) Has the school been notified?
(4) If no to (3), why not?
(5) What is the estimated cost of
the works?
CONDITIONING
1045. Hon AMBER-JADE SANDERSON to the
Leader of the House representing the Minister for Finance:
I
refer to question without notice 1026 and the Minister for Education's
advice that the Department of Finance has completed its validation for the
scope of work to provide power infrastructure upgrades to Morley Senior High
School.
(1) What is the time frame for
completed works?
(2) Which department is overseeing
the works?
(3) Has the school been notified?
(4) If no to (3), why not?
(5) What is the estimated cost of
the works?
AnswerView source ↗
On behalf of the Leader of the House
representing the Minister for Finance, I thank the honourable member for some
notice of the question. The Department of Finance advises —
(1)–(5) Building
Management and Works is managing the proposed power infrastructure upgrades to
Morley Senior High School on behalf of the Department of Education. It is anticipated
that the tender for the upgrade works will be released to market by November
2016, after which the estimated cost will be known. The project is scheduled
for completion by February 2017.
representing the Minister for Finance, I thank the honourable member for some
notice of the question. The Department of Finance advises —
(1)–(5) Building
Management and Works is managing the proposed power infrastructure upgrades to
Morley Senior High School on behalf of the Department of Education. It is anticipated
that the tender for the upgrade works will be released to market by November
2016, after which the estimated cost will be known. The project is scheduled
for completion by February 2017.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.