❓ A WA parliamentary question regarding the northern railway extension to Butler/Brighton, including timelines, costs, and station construction. The government confirms the project is a priority with construction planned for 2011-2014.
AnsweredQoN 1376Legislative Council
QuestionView source ↗
(1) Has the State Government finalised the priorities for state infrastructure that the Minister referred to in answer (1) of question No. 374?
(2) If no to (1), when does the Minister expect the priorities to be determined?
(3) Is the construction of the northern railway extension to Butler/Brighton one of these priorities?
(4) If no to (3), why not?
(5) If yes to (3), when will construction of the northern railway extension commence?
(6) When will construction be completed?
(7) What is the estimated cost?
(8) When will construction of Butler Station commence?
(9) When will construction be completed?
(10) What is the estimated cost?
(11) When will construction of Brighton Station commence?
(12) When will construction be completed?
(13) What is the estimated cost?
(14) What is the total estimated cost of the extension of railway line from Clarkson to Brighton?
(15) When will the master plan for the extension commence, and when will it be completed?
(2) If no to (1), when does the Minister expect the priorities to be determined?
(3) Is the construction of the northern railway extension to Butler/Brighton one of these priorities?
(4) If no to (3), why not?
(5) If yes to (3), when will construction of the northern railway extension commence?
(6) When will construction be completed?
(7) What is the estimated cost?
(8) When will construction of Butler Station commence?
(9) When will construction be completed?
(10) What is the estimated cost?
(11) When will construction of Brighton Station commence?
(12) When will construction be completed?
(13) What is the estimated cost?
(14) What is the total estimated cost of the extension of railway line from Clarkson to Brighton?
(15) When will the master plan for the extension commence, and when will it be completed?
AnswerView source ↗
Answered
27 November 2009
Responded by
Minister for Transport
Response time
17 days
(1) No
(2)After proper consideration
(3) Yes
(4) Not Applicable
(5) 2011
(6) 2014
(7) $240.73m
(8) The need will be reviewed five years after Brighton is commissioned
(9) As above (8)
(10) The cost will be estimated when and if the need for the station is demonstrated
(11) 2011
(12) 2014
(13) The cost is included in the $240.73m allocation
(14) $240.73m
(15) Master Planning has been completed
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
(2)After proper consideration
(3) Yes
(4) Not Applicable
(5) 2011
(6) 2014
(7) $240.73m
(8) The need will be reviewed five years after Brighton is commissioned
(9) As above (8)
(10) The cost will be estimated when and if the need for the station is demonstrated
(11) 2011
(12) 2014
(13) The cost is included in the $240.73m allocation
(14) $240.73m
(15) Master Planning has been completed
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.