A WA parliamentary question regarding the sale and development timeline of lots 5 and 6 at Elizabeth Quay, specifically concerning the negotiation period with Brookfield. The Minister provides specific dates for negotiation milestones but defers on development timelines.

AnsweredQoN 870Legislative Council
Asked
20 August 2015
Portfolio
Planning

QuestionView source ↗

ELIZABETH
QUAY — LOTS 5 AND 6
870. Hon AMBER-JADE SANDERSON to the
minister representing the Minister for Planning:
I refer to potential sale of lots 5
and 6 at Elizabeth Quay.
(1) When did the exclusive
negotiation period end?
(2) When was Brookfield selected as
the preferred bidder?
(3) When is the current negotiation
period expected to end?
(4) What is the current time frame
for a development application to be submitted?
(5) What is the expected
construction commencement date?
(6) What is the expected
construction completion date?

AnswerView source ↗

I thank the member for some notice
of the question.
(1) The exclusive working period has
not ended.
(2) It was on 13 April 2015.
(3) The exclusive working period
ends on 29 July 2016.
(4)–(6)
These milestones will be negotiated as part of the project development
agreement, which will be finalised at the end of the exclusive working period.
The project development agreement will ensure development of the site is
undertaken in a timely manner.