Mr. Buswell questions the adherence to the Environmental Monitoring and Management Plan (EMMP) for the Port Geographe project, specifically regarding water and sediment quality testing. The response indicates non-compliance by the proponent in early years, leading to a warning.

AnsweredQoN 1399Legislative Assembly
Asked
16 August 2006
Portfolio
the Environment

QuestionView source ↗

Referring to the Environmental Monitoring and Management Plan (EMMP) associated with the Port Geographe project in Busselton particularly to the water quality monitoring as specified in section 3 of the EMMP.
The EMMP requires that sampling be conducted on a semi-annual basis (January and July) during the first 4 years after construction and quarterly during the fifth year -
(1) Have these testing requirements been adhered to in accordance with the EMMP over each of the first 5 years as per sections -
(a) 3.4.2 Water Quality;
(b) 3.4.3 Metals in Biotas; and
(c) 3.4.4 Sediment Quality?
(2) Please provide the test results from each of the above sections throughout the first five years.
(3) Please provide details of the testing regime currently in place.

AnswerView source ↗

Answered
26 September 2006
Responded by
Minister for the Environment
Response time
41 days
(b) 3.4.3 Metals in Biotas; and (c) 3.4.4 Sediment Quality?
(c) 3.4.4 Sediment Quality?
(2) Results of water quality monitoring submitted to the DEC since November 2005 is attached in Attachments 1 & 2 [see tabled paper no] and the sampling locations in Attachment 3 [see tabled paper no]. Results for the first five years cannot be provided since the proponent failed to routinely conduct monitoring prior to 2005. This was the basis of the non-compliance warning issued to the proponent in 2005. (3) The current testing regime is described in Attachment 4 [see tabled paper no].
Results for the first five years cannot be provided since the proponent failed to routinely conduct monitoring prior to 2005. This was the basis of the non-compliance warning issued to the proponent in 2005. (3) The current testing regime is described in Attachment 4 [see tabled paper no].
(3) The current testing regime is described in Attachment 4 [see tabled paper no].