Question regarding the status, cost, and future plans for the 115 Hamilton Hill residential development, a project on the site of the former Hamilton Senior High School. The answer provides a general update on the project's progress, funding, and future stages, but lacks specific details requested.

AnsweredQoN 1738Legislative Assembly
Asked
17 February 2026
Portfolio
Planning and Lands; Housing and Works; Health Infrastructure

QuestionView source ↗

I refer to the 115 Hamilton Hill residential development on the site of the former Hamilton Senior High School and I ask: (a) at what stage is this development at; (b) will the development still provide the intended estimated 330 homes to market: (i) if yes, by when; (c) of the intended dwellings, how many will be private, social, and affordable tenures; (d) will the development be staged: (i) if yes, what are the timeframes of this staging; (e) what is the forecast completion date for all dwellings to be delivered; (f) what plans are there to develop associated community and commercial facilities to support the redevelopment: (i) what stage are these facilities at; (g) what is the total cost of the project to date; and (h) what is the anticipated total final cost of the project?

AnswerView source ↗

Answered
17 March 2026
Responded by
Minister for Planning and Lands; Housing and Works; Health Infrastructure
Response time
9 days
(a-h) The OneOneFive Hamilton Hill project (Hamilton Hill) is a successful example of an urban renewal project under the Cook Labor Government.
Approximately $37 million has been expended to date to deliver 150 lots, with an additional 89 lots to be delivered. $11 million was received in additional funding to support the delivery of the additional lots.
Social housing has been provisioned for within the estate.
As is standard industry practice, remaining lots will be released in stages and announcements of these releases will be made in due course.
The local structure plan proposes 300 dwellings however, final built form outcomes will be dependent on private proponents.
Purchasers set construction timeframes, built form design and occupation in line with development conditions.
Stage one public open space has been delivered, along with creation of a lot which has been sold to a private proponent to be developed as a childcare centre. Stage two public open space is currently under construction.