Mr. Zempilas asks about the completion dates of 21 modular homes built as part of the Modular Build Program in regional WA. The Minister provides the completion dates for each location, with all homes now completed.

AnsweredQoN 1424Legislative Assembly
Asked
3 December 2025
Portfolio
Planning and Lands; Housing and Works; Health Infrastructure

QuestionView source ↗

I refer to the State Government's media statement released on March 15 2022 titled "Factory homes help speed up delivery of social housing in regional WA" promoting phase two of the Modular Build Program, and I ask: (a) On what date was construction completed for each of the following 21 modular homes in each of the following towns/cities as part of the Modular Build Program: (i) Two in Leonora; (ii) Two in Kalgoorlie; (iii) Five in Geraldton; (iv) Six in Manjimup; (v) Four in Katanning; and (vi) Two in Albany; and (b) For any of the homes listed above that have not yet been completed, please provide a breakdown of the current timetable for completion for each outstanding home?

AnswerView source ↗

Answered
17 February 2026
Responded by
Minister for Planning and Lands; Housing and Works; Health Infrastructure
Response time
3 days
I thank the Member for some notice of the question.
a)    The 21 modular homes were completed as follows:
(i)          Two homes in Leonora completed February 2023
(ii)          Two homes in Kalgoorlie completed March 2023
(iii)          Five homes in Geraldton completed May 2023
(iv)          Six homes in Manjimup completed October 2022
(v)          Four homes in Katanning completed May 2024
(vi)          Two homes in Albany completed June 2023
Not applicable