Hon Jim Chown asks about the current operating costs of the public transport rail system and the projected cost increase after the completion of Metronet. The Minister provides the current operating costs and subsidy rates but states that future costs are still being determined.

AnsweredQoN 610Legislative Council
Asked
11 June 2019
Portfolio
Transport

QuestionView source ↗

PUBLIC TRANSPORT —
TRAIN SERVICES — OPERATING COSTS
610. Hon JIM CHOWN to the minister representing the Minister
for Transport:
(1) What are the full operating
costs of running the public transport rail system as it exists today?
(2) What will be
the cost increase to the public transport rail system once Metronet has been
completed?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1) For the 2018–19
financial year, the total operating cost for Transperth train and Transwa rail
services is estimated at $364.1 million. Transperth train services are
subsidised at a rate of 58.1 per cent and Transwa rail services at 78.2 per
cent.
(2) Operating
costs associated with Metronet projects are being determined through the
planning process.