Hon. Norman Moore questions the Minister regarding the land resumption for the new police headquarters in Northbridge, following delays to the project. The Minister confirms the land hasn't been purchased but the resumption process has begun and is being appealed.

AnsweredQoN 398Legislative Council
Asked
6 June 2007
Portfolio
Police and Emergency Services

QuestionView source ↗

POLICE HEADQUARTERS, NORTHBRIDGE - LAND RESUMPTION
I refer the minister to the recent announcement that the plan for a new police headquarters in Northbridge has been set back. (1) Has the government purchased the land it sought to resume in Northbridge for the project? (2) If not, will the government now stop the land resumption process to enable an open and transparent planning process to take place; and, if not, why not? Hon JON FORD

AnswerView source ↗

I thank the member for some notice of this question. The Minister for Police and Emergency Services has supplied the following answer - (1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
(1) Has the government purchased the land it sought to resume in Northbridge for the project? (2) If not, will the government now stop the land resumption process to enable an open and transparent planning process to take place; and, if not, why not? Hon JON FORD replied: I thank the member for some notice of this question. The Minister for Police and Emergency Services has supplied the following answer - (1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
(2) If not, will the government now stop the land resumption process to enable an open and transparent planning process to take place; and, if not, why not? Hon JON FORD replied: I thank the member for some notice of this question. The Minister for Police and Emergency Services has supplied the following answer - (1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
Hon JON FORD replied: I thank the member for some notice of this question. The Minister for Police and Emergency Services has supplied the following answer - (1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
I thank the member for some notice of this question. The Minister for Police and Emergency Services has supplied the following answer - (1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
(1) No. (2) The land resumption process has commenced, and the owner is appealing against the decision.
(2) The land resumption process has commenced, and the owner is appealing against the decision.