Hon Kim Chance asks about the status and funding of the Walkaway Pumping Station and pipeline upgrade. The Minister confirms contracts are not yet awarded and provides expected timelines, clarifying funding is from the existing capital budget.

AnsweredQoN 42Legislative Council
Asked
25 November 2008
Portfolio
Water

QuestionView source ↗

(1) Have contracts for the construction of the Walkaway Pumping Station and pipeline upgrade been awarded?
(2) If no to (1), when it is expected that the contracts for construction of the Walkaway Pumping Station and pipeline upgrade will be awarded?
(3) Is it intended that the cost of the Walkaway Pumping Station and pipeline upgrade will be treated as a component of the ‘Royalties for Regions’ package?

AnswerView source ↗

Answered
9 March 2009
Responded by
Parliamentary Secretary representing the Minister for Water
Response time
104 days
(1) No.
(2) The contract is expected to be awarded for the Allanooka pipeline in late February 2009 and the contract for the Walkaway Pump Station in approximately May/June 2009.
(3) The Water Corporation has prioritised these works within the existing capital budget approved by the Government.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more