Hon Barbara Scott asks about the infill sewerage program in Hamilton Hill, Spearwood, and Munster, questioning timelines, costs, and budget inclusion. Hon Kim Chance responds with project timelines, cost estimates, and defers on budget specifics.

AnsweredQoN 117Legislative Council
Asked
4 April 2006
Portfolio
Water Resources

QuestionView source ↗

INFILL SEWERAGE PROGRAM - HAMILTON HILL, SPEARWOOD AND MUNSTER AREAS
I refer to the infill sewerage program. According to the Water Corporation plan of September 2001, work on infill sewerage provision in the Hamilton Hill, Spearwood and Munster areas was to have been undertaken in 2003-04. (1) When can the residents of Spearwood, Hamilton Hill and Munster, and in particular those in Ross Court, Spearwood, expect to have infill sewerage installed? (2) Can the minister confirm whether an estimate of the cost for this area has been done; and if so, what is the cost? (3) Will this be included in the May 2006 budget? Hon KIM CHANCE

AnswerView source ↗

I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(1) When can the residents of Spearwood, Hamilton Hill and Munster, and in particular those in Ross Court, Spearwood, expect to have infill sewerage installed? (2) Can the minister confirm whether an estimate of the cost for this area has been done; and if so, what is the cost? (3) Will this be included in the May 2006 budget? Hon KIM CHANCE replied: I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(2) Can the minister confirm whether an estimate of the cost for this area has been done; and if so, what is the cost? (3) Will this be included in the May 2006 budget? Hon KIM CHANCE replied: I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(3) Will this be included in the May 2006 budget? Hon KIM CHANCE replied: I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
Hon KIM CHANCE replied: I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
I thank the member for some notice of this question. I think the member is the first to ask the unanswerable question! (1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(1) Several projects are scheduled for Spearwood and Hamilton Hill in the infill sewerage program. The first of these projects will commence in 2006-07, and all projects for these areas will be completed by 2013. Under current funding levels, Ross Court, Spearwood, is scheduled for construction in 2012. There is no infill sewerage project in Munster. (2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(2) Preliminary estimates have been undertaken for the Spearwood and Hamilton Hill projects. The estimate is around $12.6 million. (3) The state government budget for 2006-07 will be announced in May 2006.
(3) The state government budget for 2006-07 will be announced in May 2006.