WA Parliamentary Question regarding the Bunbury to Albany Gas Pipeline Project Steering Committee, its membership, meeting dates, and related reports. The project was put on hold in late 2013.

AnsweredQoN 5388Legislative Assembly
Asked
28 April 2016
Portfolio
State Development

QuestionView source ↗

I refer to the Bunbury to Albany Gas Pipeline Project Steering Committee and I ask: (a) please provide the current membership of the Project Committee; (b) please provide the dates of meetings of the Project Committee for each of the following years: (i) 2013; (ii) 2014; (iii) 2015; and (iv) 2016; and (c) since the GHD Report "Department of State Development Bunbury to Albany Pipeline Project Gas Distribution and Customer Construction Cost Estimates Rev C" of June 2013, have there been any other external or consultants reports regarding the project, and if yes, what are the name of these reports and who authored each such report?

AnswerView source ↗

Answered
15 June 2016
Responded by
Minister for State Development
Response time
48 days
The Department of State Development advises:
(a)         In November 2013 commercial and financial work regarding the pipeline, including the functions of the Steering Committee, was put on hold when the Government considered alternate project options.
(b) - (i)  The Project Steering Committee met on 26 March 2013 and 13 August 2013.
(b-ii)-(b-iv)
Not applicable
(c)         External reports produced since June 2013 were:
Bunbury to Albany Gas Pipeline – Feasibility Study Manjimup to Mt Barker: Level 1 Flora and Fauna Assessment, October 2013, GHD.
Bunbury to Albany Gas Pipeline – Environmental Constraints Analysis, December 2013, SKM.