Dr. Steve Thomas questions the Minister for Transport regarding the budget, funding split, and completion timeline of the Bussell Highway duplication project, highlighting discrepancies between the Minister's commitment and Main Roads' website.

AnsweredQoN 852Legislative Council
Asked
14 August 2024
Portfolio
Transport

QuestionView source ↗

BUSSELL HIGHWAY —
DUPLICATION
852. Hon Dr STEVE THOMAS to the minister representing the
Minister for Transport:
I refer to the duplication of a 17-kilometre
section of Bussell Highway between Bunbury and Busselton, and the minister's
commitment of project completion by the end of calendar year 2024.
(1) From a starting
budget of $80 million, with works commencing in January 2020, what is the
current project budget completion allocation?
(2) What is the
apportionment of federal funding to state funding on this project and, as at 14
August 2024, what are the current respective amounts?
(3) Given that the Main Roads website detailing this
project, which was last updated on 31 July 2024, specifies that the
project will be completed in early 2025, and the minister's commitment
to completion by the end of 2024, is Main Roads or the minister correct about
the timeframe for completion?

AnswerView source ↗

I thank the honourable member for some notice of the
question. The following answer has been provided to me by the Minister for
Transport.
(1)–(3)
Details of project funding profiles can be found in the state budget papers.
Completion is expected in the coming months and will be announced in due
course.