Alanna Clohesy asks the Treasurer about the cash flow for the Metro Area Express light rail project, specifically comparing the initial 2018 completion date estimates with the revised 2020 completion date. The Treasurer provides some figures and refers the member to the budget papers for further details.

AnsweredQoN 597Legislative Council
Asked
19 September 2013
Portfolio
minister representing the Treasurer

QuestionView source ↗

MAX LIGHT RAIL — ANNUAL CASH FLOW
597. Hon ALANNA CLOHESY to the
minister representing the Treasurer:
I refer to Treasury's estimated total cost of $1.882 billion
for the proposed Metro Area Express light rail.
(1) When the project was due for completion in 2018, what was

(a) the base cost cash flow for
each year of the project; and
(b) the escalated cost cash flow
for each year of the project?
(2) Now that the project is due for completion by 2020, what
is —
(a) the base cost cash flow for each
year of the project; and
(b) the escalated cost cash flow
for each year of the project?

AnswerView source ↗

I thank the honourable member for some notice of this
question.
(1) (a) Nil; $65 million; $134 million; $604 million.
(b) Nil; $70 million; $150 million;
$712 million.
(2) (a) A base cash flow is not available.
(b) The member
should refer, once again, to page 374 of the 2013-14 Budget Statements , budget paper No 2, volume 1, where this is laid
out for each of the years required.
I seek leave to table the attached
document and have it incorporated into Hansard .
The
PRESIDENT : Once again, would the minister please identify what she is
seeking to have incorporated in Hansard ,
because it may be a full document or it may be one page.
Hon HELEN MORTON : Thank you, Mr President. It is one
page of the budget papers that outlines the information that the member is
seeking.
Leave granted. [See paper 656.]
[See page 4482.]