❓ Question regarding the funding, scope, and timeline for the Curtin Avenue realignment project as outlined in the WA Budget Paper 2. The answer provides funding details and indicates planning is underway, but the construction timeframe is still dependent on planning outcomes.
AnsweredQoN 4523Legislative Assembly
QuestionView source ↗
(1) I refer to page 812 of Budget Paper 2 and footnote (d) which refers to major works to include the realignment of Curtin Avenue and I ask; how much is allocated to this specific project? (2) What work is being done on this realignment? (3) What is the timeframe for this project?
AnswerView source ↗
Answered
14 October 2015
Responded by
Minister for Transport
Response time
35 days
(1) As at October 2015, funding of $40m for this project is currently allocated over the 2016/17 to 2018/19 financial years.
(2) Main Roads is progressing planning, investigation and development works for this project.
(3) The construction timeframe is dependent on the planning development works.
(2) Main Roads is progressing planning, investigation and development works for this project.
(3) The construction timeframe is dependent on the planning development works.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.