Question regarding contaminated soil removal during the Southern Rail Link project. Minister denies encountering 100,000 cubic metres of contaminated soil, stating the contract covers 25,250 cubic metres, and that volume hasn't been reached.

AnsweredQoN 725Legislative Assembly
Asked
11 November 2004
Portfolio
Planning and Infrastructure

QuestionView source ↗

I refer the minister to the contract for the central business district tunnel section of Labor’s southern rail link, for which the Government has accepted liability for the removal of any contaminated soil. (1) Will the minister confirm that the contractors have encountered more than 100 000 cubic metres of contaminated soil during drilling and excavation in both the Esplanade and the Perth yard sites? (2) If so, what is the nature of the contamination and the estimated cost of removing the contaminated soil? (3) What is the expected delay to the project from removing the contaminated soil? Ms A.J. MacTIERNAN

AnswerView source ↗

(1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
(1) Will the minister confirm that the contractors have encountered more than 100 000 cubic metres of contaminated soil during drilling and excavation in both the Esplanade and the Perth yard sites? (2) If so, what is the nature of the contamination and the estimated cost of removing the contaminated soil? (3) What is the expected delay to the project from removing the contaminated soil? Ms A.J. MacTIERNAN replied: (1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
(2) If so, what is the nature of the contamination and the estimated cost of removing the contaminated soil? (3) What is the expected delay to the project from removing the contaminated soil? Ms A.J. MacTIERNAN replied: (1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
(3) What is the expected delay to the project from removing the contaminated soil? Ms A.J. MacTIERNAN replied: (1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
Ms A.J. MacTIERNAN replied: (1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
(1)-(3) It is extraordinary that I can be expected to answer a question of that detail without having been given any notice of it. Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
Several members interjected. The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
The SPEAKER: Order, members! I could not hear what the minister was trying to say because she was being howled down. I call the member for Warren-Blackwood to order for the second time. Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
Ms A. J. MacTIERNAN: What an absolute joke! I am supposed to be down on the job every day watching what is coming out of the tunnel, getting my stereo plotter out, making calculations and saying how much dirt is there. Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
Several members interjected. The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
The SPEAKER: Order, members! I call to order the Leader of the National Party and the member for Dawesville. Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.
Ms A.J. MacTIERNAN: I actually take it as a compliment because I know the member for Carine has such great confidence in my abilities that she believes I will be across all these things. I can confirm that no such volumes of contaminated soil have been removed from the site. I can explain the funding mechanism. The contract provides for the removal of contaminated soil up to the volume of 25 250 cubic metres. I can further confirm that nothing like this volume has been removed. We do not anticipate that there will be any significant volume of contaminated soil greater than the 25 250 cubic metres that we have made provision for.