Hon Adele Farina asks about the progress and expected completion date of the Busselton Health Campus construction. The Minister provides an update indicating the project is 50% complete and on schedule for October 2014.

AnsweredQoN 564Legislative Council
Asked
31 October 2013
Portfolio
Health

QuestionView source ↗

I refer to Budget Paper No. 2, Volume 1 at page 148 "Asset Investment Program - works in progress, line item "Busselton Health Campus", and ask: (a) what is the current status of the hospital; and (b) what is the expected completion date for the hospital?

AnswerView source ↗

Answered
4 December 2013
Responded by
Parliamentary Secretary representing the Minister for Health
Response time
34 days
Answer as at 22 November 2013:
(a) Construction of the Busselton Health Campus is approximately 50% complete.  The last major concrete pour occurred in September 2013. Interior fit out has commenced. Temporary roads are in place to maintain site access and the first of the new car parks is being used by staff and patients.  All existing services continue to be provided from the site.
(b) Construction of the main health campus building is on schedule for completion in October 2014.