❓ Question on Notice regarding Perth Airport road project submissions to Infrastructure Australia, seeking details on project specifics, costs, timelines, funding, and the Perth Airport transport master plan. The Minister provides some details but notes funding and negotiations are ongoing.
AnsweredQoN 1196Legislative Council
QuestionView source ↗
INFRASTRUCTURE AUSTRALIA SUBMISSION — PERTH AIRPORT ROAD PROJECTS
I refer to the Premier’s announcement last week regarding the state government’s latest submission to Infrastructure Australia, which included road upgrades around Perth Airport as the government’s number one priority. (1) Can the minister detail all the road projects surrounding the airport that were included in the state government’s submission? (2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN
I refer to the Premier’s announcement last week regarding the state government’s latest submission to Infrastructure Australia, which included road upgrades around Perth Airport as the government’s number one priority. (1) Can the minister detail all the road projects surrounding the airport that were included in the state government’s submission? (2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN
AnswerView source ↗
I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(1) Can the minister detail all the road projects surrounding the airport that were included in the state government’s submission? (2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(5) No; it is expected to be completed by mid-2010.
(1) Can the minister detail all the road projects surrounding the airport that were included in the state government’s submission? (2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(2) What is the estimated total cost for each of these projects? (3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(3) What is the government’s preferred time line for work on each of these projects to commence and to be completed? (4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(4) Has any money already been allocated to any of these projects by either the state or federal government; and, if so, how much by each government? (5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(5) Has the Perth Airport transport master plan been completed; and, if not, when does the minister expect the plan to be completed? Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon SIMON O’BRIEN replied: I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
I thank the honourable member for some notice of this question. (1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(1) A package of required works is currently being developed and will include works on Tonkin Highway, Great Eastern Highway to Roe Highway, Leach Highway-Orrong Road to the airport, and Orrong Road-Great Eastern Highway to Leach Highway. (2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(2) The total estimated cost is currently $600 million. Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon Ken Travers : Is that for each of the projects? Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
Hon SIMON O’BRIEN : No; that is the total cost. (3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(3) It is expected that delivery of various works related to the projects could be over the period 2014 to 2016, depending on the outcome of funding arrangements and negotiations currently under consideration by the state and federal governments. (4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(4) There is currently $19 million allocated in the forward estimates. (5) No; it is expected to be completed by mid-2010.
(5) No; it is expected to be completed by mid-2010.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.