The Minister for the Environment and Heritage confirms approval dates for the Wokalup and Samson Brook Dams and clarifies the Stirling Dam connection was authorised as a General Work under the Water Agencies (Powers) Act.

AnsweredQoN 750Legislative Assembly
Asked
25 February 2003
Portfolio
the Environment and Heritage

QuestionView source ↗

Has approval been provided to the Water Corporation to proceed with the Wokalup Dam and the Samson Brook Dam and the connecting of these dams to the Stirling Dam to Perth pipe?

AnswerView source ↗

Answered
18 March 2003
Responded by
Minister for the Environment and Heritage
Response time
21 days
* Wokalup Dam: 6 November 2002 * Samson Brook Dam: 13 September 2002 The "Connection to the Stirling Dam to Perth pipe" is a General Works and not a Major Works and was authorised by the Water Corporation under the authority of the Water Agencies (Powers) Act on 1 August 2002.
The "Connection to the Stirling Dam to Perth pipe" is a General Works and not a Major Works and was authorised by the Water Corporation under the authority of the Water Agencies (Powers) Act on 1 August 2002.