A WA parliamentary question regarding funding, scope, commencement, and completion of a station upgrade project, focusing on accessibility, aesthetics, and structural maintenance. The project is expected to be completed by late 2007.

AnsweredQoN 97Legislative Assembly
Asked
29 June 2005
Portfolio
Planning and Infrastructure

QuestionView source ↗

(b) what will the $436,000 allocated in 2005-06 be used for; (c) what works will be undertaken with the total estimated funds of $3,750,000; (d) when will construction work commence; and (e) when will the project be completed?
(c) what works will be undertaken with the total estimated funds of $3,750,000; (d) when will construction work commence; and (e) when will the project be completed?
(d) when will construction work commence; and (e) when will the project be completed?
(e) when will the project be completed?
2007/08 $1 250 000. 2008/09 No funds allocated as the project will be completed. (b) Primarily, design and documentation. (c) The design has reached the concept stage with scope still to be finalised. Key objectives of the project are: · Make improvements to the station so that it meets Disability Discrimination Act standards. · Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
2008/09 No funds allocated as the project will be completed. (b) Primarily, design and documentation. (c) The design has reached the concept stage with scope still to be finalised. Key objectives of the project are: · Make improvements to the station so that it meets Disability Discrimination Act standards. · Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
(b) Primarily, design and documentation. (c) The design has reached the concept stage with scope still to be finalised. Key objectives of the project are: · Make improvements to the station so that it meets Disability Discrimination Act standards. · Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
(c) The design has reached the concept stage with scope still to be finalised. Key objectives of the project are: · Make improvements to the station so that it meets Disability Discrimination Act standards. · Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
· Make improvements to the station so that it meets Disability Discrimination Act standards. · Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
· Aesthetic improvement of station building and precinct, particularly from Helena Street. · Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
· Address maintenance issues with regard to the structure. (d) Late 2006. (e) Late 2007.
(d) Late 2006. (e) Late 2007.
(e) Late 2007.

AnswerView source ↗

Answered
16 August 2005
Responded by
Minister for Planning and Infrastructure
Response time
48 days
(a) 2006/07 $2 000 000.
2007/08 $1 250 000.
2008/09 No funds allocated as the project will be completed.
(b) Primarily, design and documentation.
(c) The design has reached the concept stage with scope still to be finalised. Key objectives of the project are:
· Make improvements to the station so that it meets Disability Discrimination Act standards.
· Aesthetic improvement of station building and precinct, particularly from Helena Street.
· Address maintenance issues with regard to the structure.
(d) Late 2006.
(e) Late 2007.