The question seeks data on Western Power's assessment times for commercial project applications. The answer indicates no backlog but reveals a significant number of applications exceeding the 20-day assessment timeframe.

AnsweredQoN 759Legislative Council
Asked
19 May 2022
Portfolio
Energy

QuestionView source ↗

I refer to commercial applications received by the validation unit within Western Power, and I ask: (a) how many commercial projects are currently waiting to be assessed at the validation stage since October 2021; and (b) how many commercial applications have exceeded the 20 business day timeframe for technical assessment stage since October 2021?

AnswerView source ↗

Answered
9 August 2022
Responded by
Parliamentary Secretary representing the Minister for Energy
Response time
11 days
(a) There are no commercial applications waiting to be assessed, as all new requests are allocated and put under assessment within 10 business days of receipt.
(b) Of 1386 commercial applications assessed from October 2021 to the end of April 2022, 387 assessments exceeded the 20-business day timeframe, noting that customer wait time is included in the recording of business days to complete the application assessment.