I refer to the Regional Grants Scheme funding to the Shire of Carnarvon, and I ask -
(1) For the grant of $180 000 for Carnarvon Aquatic Centre improvements, -
(a) what is the total cost of the improvements;
(b) what is the source and amount of any other funding for these improvements;
(c) what are the details of the improvements to be undertaken;
(d) has the work commenced and if not, when is it due to commence;
(e) has the work been completed and if so, when was it completed; and
(f) if the work is not completed, when will it be completed?
(2) For the grant of $250 000 for integrated water supply delivery, -
(a) what is the total cost of the project;
(b) what is the source and amount of any other funding for this project;
(c) what are the details of the work to be undertaken;
(d) has the work commenced and if not, when is it due to commence;
(e) has the work been completed and if so, when was it completed;
(f) if the work is not completed, when will it be completed; and
(g) what is the role of the Water Corporation, which operates and maintains water supplies in the Gascoyne Region, in this particular project?
(3) For the grant of $500 000 for fascine urgent remedial works and enhancement design, -
(a) what is the total cost of the project;
(b) what is the source and amount of any other funding for this work;
(c) what are the details of the work to be undertaken;
(d) has the work commenced and if not, when is it due to commence;
(e) has the work been completed and if so, when was it completed; and
(f) if the work is not completed, when will it be completed?

AnswerView source ↗

Answered
9 September 2010
Responded by
Parliamentary Secretary representing the Minister for Regional Development
Response time
71 days
(1)
(a) Total project cost at time of application for GRGS was $205,000 (GST Exclusive)
(b) $25,000 - Own contribution
(c) Contracting consultants to develop a Master Plan to implement the findings of the Needs Analysis and Feasibility Study; and essential remediation works to existing swimming pool facility including replacement of balance tank lid, safety signage, replacement of shade structures, restorative work in toilets and shower facilities and restorative work on concourse.
(d) Yes.
(e) No.
(f) September 2010.
(2)
(a) Total project cost at time of application for GRGS was $287,500 (GST Exclusive)
(b) $37,500 - Own contribution
(c) Design and development of all components and requirements necessary for the successful implementation of an integrated water supply delivery system for the town of Carnarvon's urban landscape needs; and implementation works for the town of Carnarvon's integrated water supply delivery system.
(d) Yes.
(e) No.
(f) March 2011.
(g) The Water Corporation supplies two of the five water resources currently in use in the Shire of Carnarvon and will play a major role in partnering the Shire of Carnarvon to identify solutions for a more integrated and efficient water supply delivery system.
(3)
(a) Total project cost at time of application for GRGS was $575,000 (GST Exclusive).
(b) $75,000 - Own contribution
(c) Whole of waterfront design/development and continuation of the Carnarvon Surge Wall project; and contract works on remediation to the Fascine wall and footpath.
(d) Yes.
(e) No.
(f) March 2011.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more