For each Government-funded end-of-life tyre recycling project:
(a) what funding agreement conditions apply;
(b) what reporting obligations apply;
(c) what milestone payments have been made;
(d) what milestones remain outstanding;
(e) has any milestone been delayed, varied, waived or extended; and
(f) if yes to (e), why?
Minister for the Environment
34 calendar days total
5 sitting days total
1 sitting day after grace period
(a) Recycling Modernisation Fund grant recipients enter into a Deed of Grant with the Department of Water and Environmental Regulation and includes detailed funding arrangements, timeframes and grantee obligations.
(b) The Recycling Modernisation Fund Deed of Grant specifies the reporting obligations for each project including quarterly, annual and milestone reports.
(c) 29 of 31 milestones have been achieved, and 26 milestone payments have been made across the six tyre projects awarded funding under the Recycling Modernisation Fund.
(d) No further milestones remain outstanding under tyre project funding agreements.
(e) Yes, four individual projects funded under the Recycling Modernisation Fund experienced delays requiring six milestone extensions that were formalised through variations to the Deed of Grant. No milestones have been waived for tyre-recycling projects funded under the Recycling Modernisation Fund.
(f) These large complex recycling infrastructure projects have experienced delays due to a range of issues including difficulties accessing the required expertise, cost escalations, labour shortages, lack of availability of suitable premises.