Hon Simon O'Brien asks the Minister for Planning and Infrastructure about the costs and details of water infrastructure modifications required for the New MetroRail project. The Minister, Hon Adele Farina, requests the question be put on notice due to the complexity of gathering the information.

AnsweredQoN 422Legislative Council
Asked
7 June 2007
Portfolio
Planning and Infrastructure

QuestionView source ↗

WATER CORPORATION INFRASTRUCTURE - NEW METRORAIL
I refer to my question to the Minister for Water Resources asked in the Legislative Council on Thursday, 31 May 2007 concerning costs for modification of water supply, drainage and sewerage infrastructure made necessary by the construction of the New MetroRail southern suburbs railway project. (1) What were/are the necessary modifications? (2) What was the cost of these modifications - (a) in total; and (b) if the works were broken down into individual packages or programs - those individual amounts? (3) To whom will the cost of these modifications be paid, and when? Hon ADELE FARINA

AnswerView source ↗

I thank the honourable member for some notice of this question. A large number of water and sewerage modifications have been carried out in different contracts for the southern suburbs railway. An amount of research is required to collate the information to provide the answer. The minister therefore requests that the question be put on notice.
(1) What were/are the necessary modifications? (2) What was the cost of these modifications - (a) in total; and (b) if the works were broken down into individual packages or programs - those individual amounts? (3) To whom will the cost of these modifications be paid, and when? Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. A large number of water and sewerage modifications have been carried out in different contracts for the southern suburbs railway. An amount of research is required to collate the information to provide the answer. The minister therefore requests that the question be put on notice.
(2) What was the cost of these modifications - (a) in total; and (b) if the works were broken down into individual packages or programs - those individual amounts? (3) To whom will the cost of these modifications be paid, and when? Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. A large number of water and sewerage modifications have been carried out in different contracts for the southern suburbs railway. An amount of research is required to collate the information to provide the answer. The minister therefore requests that the question be put on notice.
(b) if the works were broken down into individual packages or programs - those individual amounts?
Hon ADELE FARINA replied: I thank the honourable member for some notice of this question. A large number of water and sewerage modifications have been carried out in different contracts for the southern suburbs railway. An amount of research is required to collate the information to provide the answer. The minister therefore requests that the question be put on notice.
I thank the honourable member for some notice of this question. A large number of water and sewerage modifications have been carried out in different contracts for the southern suburbs railway. An amount of research is required to collate the information to provide the answer. The minister therefore requests that the question be put on notice.