ROADWORKS — RANFORD ROAD — CANNING VALE
633. Hon NICK GOIRAN to the minister representing the
Minister for Transport:
I refer to the roadworks on Ranford
Road in Canning Vale.
(1) On what date did the roadworks
commence?
(2) What was their initial budgeted
completion date?
(3) By what date are the roadworks
now scheduled to be fully complete?
633. Hon NICK GOIRAN to the minister representing the
Minister for Transport:
I refer to the roadworks on Ranford
Road in Canning Vale.
(1) On what date did the roadworks
commence?
(2) What was their initial budgeted
completion date?
(3) By what date are the roadworks
now scheduled to be fully complete?
AnswerView source ↗
I thank the honourable member for
some notice of the question. The following answer has been provided by the
Minister for Transport.
(1)–(3) The roadworks on Ranford Road saw the
construction of a significantly higher, longer and wider bridge over the
railway corridor than the previous structure. The new bridge is 1.2 metres
higher, 15 metres longer and significantly wider, with six general traffic
lanes, three in each direction, plus a dedicated bus lane and shared path on
each side. The staged approach to bridge construction has meant traffic lanes
could be maintained while the old bridge was demolished and the new bridge was built.
Traffic management for early works began in April 2020, and the project was
formally opened by the Minister for Transport on 27 May 2024.
some notice of the question. The following answer has been provided by the
Minister for Transport.
(1)–(3) The roadworks on Ranford Road saw the
construction of a significantly higher, longer and wider bridge over the
railway corridor than the previous structure. The new bridge is 1.2 metres
higher, 15 metres longer and significantly wider, with six general traffic
lanes, three in each direction, plus a dedicated bus lane and shared path on
each side. The staged approach to bridge construction has meant traffic lanes
could be maintained while the old bridge was demolished and the new bridge was built.
Traffic management for early works began in April 2020, and the project was
formally opened by the Minister for Transport on 27 May 2024.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.