A parliamentary question regarding structural problems (leaks) at Lynwood Senior High School, specifically addressing the number of reports made to the Department of Education and Training and the actions being taken to resolve the issues. The Minister's response indicates limited direct reporting to the Department of Education and that repairs are underway.

AnsweredQoN 573Legislative Council
Asked
15 August 2007
Portfolio
Education and Training

QuestionView source ↗

LYNWOOD SENIOR HIGH SCHOOL - STRUCTURAL PROBLEMS
I refer to my question of Tuesday, 14 August, in answer to which the minister advised that, during the month of July, the Department of Housing and Works received 11 reports from Lynwood Senior High School regarding leaks in various parts of the school. (1) How many reports of these or related problems and hazards were notified by the school to the Department of Education and Training itself during the month of July? (2) What is being done to address these problems at Lynwood Senior High School; and when will the problems be fixed? Hon LJILJANNA RAVLICH

AnswerView source ↗

(1) On one occasion, on or about 31 July, the school principal notified the district director at the department’s Fremantle-Peel District Education Office of the problem. (2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.
(1) How many reports of these or related problems and hazards were notified by the school to the Department of Education and Training itself during the month of July? (2) What is being done to address these problems at Lynwood Senior High School; and when will the problems be fixed? Hon LJILJANNA RAVLICH replied: (1) On one occasion, on or about 31 July, the school principal notified the district director at the department’s Fremantle-Peel District Education Office of the problem. (2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.
(2) What is being done to address these problems at Lynwood Senior High School; and when will the problems be fixed? Hon LJILJANNA RAVLICH replied: (1) On one occasion, on or about 31 July, the school principal notified the district director at the department’s Fremantle-Peel District Education Office of the problem. (2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.
Hon LJILJANNA RAVLICH replied: (1) On one occasion, on or about 31 July, the school principal notified the district director at the department’s Fremantle-Peel District Education Office of the problem. (2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.
(1) On one occasion, on or about 31 July, the school principal notified the district director at the department’s Fremantle-Peel District Education Office of the problem. (2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.
(2) The Department of Housing and Works has engaged roof plumbers to follow up on all roof leaks reported in July and to complete repairs to the affected areas.