Hon Neil Thomson asks about the anticipated completion dates for various projects under the Perth City Deal. The response redirects the questions to the relevant ministers, stating that the provided information is based on preliminary estimates from a Commonwealth government document.

AnsweredQoN 1002Legislative Council
Asked
20 October 2022
Portfolio
Leader of the House representing the Premier

QuestionView source ↗

PERTH CITY DEAL
1002. Hon NEIL THOMSON to the Leader of the House
representing the Premier:
I refer to the Perth City Deal that
was signed by the Prime Minister, the Premier and the chair commissioner of the City of Perth. This is the second part to a question
I asked about a month ago. Are the following estimated completion dates
still anticipated—yes or no—and, if not, what are the
completion dates for —
(a) the Perth Cultural Centre
redevelopment—2022;
(b) the Perth Concert Hall
redevelopment—2022;
(c) the Perth Aboriginal cultural
centre pre-feasibility study—2023;
(d) the East Perth power station
redevelopment—2024;
(e) the homelessness housing projects—2022;
and
(f) the City of Perth strategic plan—2022?

AnswerView source ↗

On behalf of the Leader of the House, I thank the honourable
member for some notice of the question. Obviously, this is dated 1 September,
so the answer is current as at that date.
Early preliminary estimated dates were included in a document
that was published by the then commonwealth government. Specific questions
regarding individual Perth City Deal projects should be directed to the
relevant minister as outlined below.
(a)–(c) The Minister for
Culture and the Arts;
(d) the Minister for Lands;
(e) the Minister for Homelessness;
and
(f) the Minister for Planning.