Hon Tom Stephens asks about the government's response to $2m+ compensation claims for damage to homes caused by the Northbridge tunnel construction. Hon M.J. Criddle responds that Main Roads WA is liaising with the contractor and its insurers, with a response expected within a fortnight.

AnsweredQoN 453Legislative Council
Asked
15 November 2000
Portfolio
Transport

QuestionView source ↗

What action has been taken by the Government in response to the compensation claims for more than $2m presented to Main Roads WA on 11 October for damage caused to homes as a result of the construction of the Northbridge tunnel? Hon M.J. CRIDDLE

AnswerView source ↗

I thank the member for some notice of this question. Main Roads Western Australia has been liaising with tunnel contractor Baulderstone Clough Joint Venture and its insurers about the claim. The contractor’s insurers have advised that it will be in a position to respond to Main Roads about the claim within a fortnight.
Hon M.J. CRIDDLE replied: I thank the member for some notice of this question. Main Roads Western Australia has been liaising with tunnel contractor Baulderstone Clough Joint Venture and its insurers about the claim. The contractor’s insurers have advised that it will be in a position to respond to Main Roads about the claim within a fortnight.
I thank the member for some notice of this question. Main Roads Western Australia has been liaising with tunnel contractor Baulderstone Clough Joint Venture and its insurers about the claim. The contractor’s insurers have advised that it will be in a position to respond to Main Roads about the claim within a fortnight.
Main Roads Western Australia has been liaising with tunnel contractor Baulderstone Clough Joint Venture and its insurers about the claim. The contractor’s insurers have advised that it will be in a position to respond to Main Roads about the claim within a fortnight.