Question regarding the cost of remediation works at a contaminated site in Exmouth undertaken by Western Power, and identification of the environmental consultants involved. Only the consultant was named.

AnsweredQoN 376Legislative Council
Asked
13 September 2017
Portfolio
Energy

QuestionView source ↗

I refer to the answer to question without notice No. 533 asked on 6 September 2017 about a contaminated site in Exmouth, lots 300 and 301 on deposited plan 406333, and ask:
(a) what was the total cost to Western Power for the remediation works carried out at this site; and
(b) who were the environmental consultants?

AnswerView source ↗

Answered
31 October 2017
Responded by
Minister for Environment representing the Minister for Energy
Response time
5 days
(b) Environmental Resources Management.