❓ The question seeks information regarding progress reports and completion status of the Matagarup Bridge construction, specifically focusing on the supply agreement between York Rizzani and the Bianco Engineering Services–Toyota Tsusho joint venture.
AnsweredQoN 618Legislative Council
QuestionView source ↗
OPTUS STADIUM —
MATAGARUP BRIDGE
618. Hon PETER COLLIER to the minister representing the
Minister for Transport:
I refer to the supply agreement
between York Rizzani and the Bianco Engineering Services–Toyota Tsusho
joint venture to manufacture the bridge decking and design features of the
pedestrian footbridge to Optus Stadium.
(1) Did Main
Roads WA or any other state government department, agency steering group or
committee receive progress reports from either Main Roads or the joint venture
on the manufacture of the bridge?
(2) If yes to
(1), on what dates were those reports received and will the minister table
copies of those reports; and, if not, why not?
(3) Was the Minister for Transport
or her office provided with copies of those reports?
(4) At the
termination of the supply agreement in May 2017, how much of the construction
of the bridge under the supply agreement was complete, including which
components?
(5) When the
supply agreement was terminated, was there an estimated completion date for the
work by the joint venture; and, if so, what was the expected completion date
and the date for delivery of the bridge to site?
MATAGARUP BRIDGE
618. Hon PETER COLLIER to the minister representing the
Minister for Transport:
I refer to the supply agreement
between York Rizzani and the Bianco Engineering Services–Toyota Tsusho
joint venture to manufacture the bridge decking and design features of the
pedestrian footbridge to Optus Stadium.
(1) Did Main
Roads WA or any other state government department, agency steering group or
committee receive progress reports from either Main Roads or the joint venture
on the manufacture of the bridge?
(2) If yes to
(1), on what dates were those reports received and will the minister table
copies of those reports; and, if not, why not?
(3) Was the Minister for Transport
or her office provided with copies of those reports?
(4) At the
termination of the supply agreement in May 2017, how much of the construction
of the bridge under the supply agreement was complete, including which
components?
(5) When the
supply agreement was terminated, was there an estimated completion date for the
work by the joint venture; and, if so, what was the expected completion date
and the date for delivery of the bridge to site?
AnswerView source ↗
I thank the Leader of the Opposition
for some notice of the question. The following information has been provided to
me by the Minister for Transport.
Due to the level of detail requested
by the member, it is requested that this question be placed on notice.
for some notice of the question. The following information has been provided to
me by the Minister for Transport.
Due to the level of detail requested
by the member, it is requested that this question be placed on notice.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.