Question regarding payments made to RMT Solutions Pty Ltd under contract DPC1641, including duration and cost. The Premier's department provided details on the days worked and total cost, confirming the contract's expiry date.

AnsweredQoN 5689Legislative Assembly
Asked
16 August 2016
Portfolio
Premier

QuestionView source ↗

Could the Premier advise what the total payment was to RMT Solutions Pty Ltd (Mr Robert Taylor), under Contract DPC1641 for the period 18 January 2016 to 2 June 2016: (a) for how many days did RMT Solutions provide services under the contract timeframes; and (b) was the contract extended beyond 2 June 2016 and, if so, for how long and for what cost?

AnswerView source ↗

Answered
21 September 2016
Response time
36 days
The Department of the Premier and Cabinet advises:
(a)        80 days
(b)        The contract expired on 2 June 2016 and the total cost for the period was $100,000