Dr. Pettitt questions the Minister for Transport regarding alternative shutdown options for the Armadale Rail Line METRONET project. The Minister confirms other options were considered but the extended shutdown was deemed least disruptive.

AnsweredQoN 392Legislative Council
Asked
11 May 2022
Portfolio
Transport

QuestionView source ↗

METRONET — ARMADALE RAIL LINE — SHUTDOWN
392. Hon Dr BRAD PETTITT to the Leader of the House
representing the Minister for Transport:
I refer to the media statement of
Sunday, 20 February 2022 titled ''Major METRONET projects to transform
the Armadale Line'' and the comment, ''While a number of shutdown
options were examined, the extended shutdown was the preferred option.''
(1) What other shutdown options
were examined?
(2) Will the
minister please table the documents related to the other shutdown options that
were examined?
(3) If no to (2), why not?

AnswerView source ↗

I thank the honourable member for
some notice of the question.
(1)–(3) As outlined in previous answers on this matter, a number
of shutdown options were considered, predominantly concerning shorter
and more frequent shutdowns over a longer period, or the extended shutdown. The
extended shutdown was determined to be the least disruptive to the community
over the longer term.