❓ Question on Notice regarding funding allocated to police facilities in Kalgoorlie, Newman, Laverton, Leonora, and Warakurna since the last State Election. The answer details maintenance and new station funding, approval dates, and completion dates.
AnsweredQoN 1903Legislative Assembly
QuestionView source ↗
Kalgoorlie $312,460 Maintenance, Minor Works and Repairs Newman $7,931 Maintenance, Minor Works and Repairs $4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005 Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Newman $7,931 Maintenance, Minor Works and Repairs $4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005 Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005 Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Newman $7,931 Maintenance, Minor Works and Repairs $4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005 Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005 Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Laverton $ 14,284 Maintenance, Minor Works and Repairs $3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005 Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Leonora $15,050 Maintenance, Minor Works and Repairs $4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
$4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008 Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Warakurna $3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
AnswerView source ↗
Answered
5 April 2007
Responded by
Minister for Police and Emergency Services
Response time
16 days
Since the last State Election on 26 February 2005, the following amounts have been spent and /or allocated to police facilities as follows:
Kalgoorlie
$312,460 Maintenance, Minor Works and Repairs
Newman
$7,931 Maintenance, Minor Works and Repairs
$4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005
Laverton $
14,284 Maintenance, Minor Works and Repairs
$3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005
Leonora
$15,050 Maintenance, Minor Works and Repairs
$4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008
Warakurna
$3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Kalgoorlie
$312,460 Maintenance, Minor Works and Repairs
Newman
$7,931 Maintenance, Minor Works and Repairs
$4,261,000 New Station - funding approved in July 2001 and station opened on 21 October 2005
Laverton $
14,284 Maintenance, Minor Works and Repairs
$3,553,000 New Station - funding approved in July 2003 and station opened on 10 August 2005
Leonora
$15,050 Maintenance, Minor Works and Repairs
$4,200,000 New Station - funding approved in July 2005 and scheduled for completion in March 2008
Warakurna
$3,872,000 New Station - funding approved in July 2004 and facility opened on 23 March 2007
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.