❓ Ms Saffioti asks the Treasurer for a list of projects delivered over budget and their respective budget vs. actual expenditure, based on the 2011-2012 Department of Treasury Annual Report. The Treasurer's response indicates that the projects are still under construction, and final costs are not yet known.
AnsweredQoN 296Legislative Assembly
QuestionView source ↗
I refer to the 2011- 2012 Department of Treasury Annual Report page 125, which states that 88 per cent of significant projects were delivered within the approved budget, and ask: (a) can the Minister provide a list of the projects that were delivered over Budget; and (b) for each of these projects over budget, can the Minister provide what the budget for those projects was, and what the actual expenditure was for each project?
AnswerView source ↗
Answered
2 September 2013
Responded by
Minister for Treasurer
Response time
83 days
The Department of Treasury advises:
(a) No. The Projects are still under construction.
(b) The anticipated final costs for the projects will not be known until construction is completed.
(a) No. The Projects are still under construction.
(b) The anticipated final costs for the projects will not be known until construction is completed.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.