Hon Ken Travers questions the Transport portfolio regarding penalties applied to the 'A' series railcar maintenance contract for breakdowns and delays between 2011-2013. The response details penalty conditions and amounts, but declines to provide data on breakdowns without penalties due to resource constraints.

AnsweredQoN 1139Legislative Council
Asked
6 May 2014
Portfolio
Transport

QuestionView source ↗

I refer to the maintenance contract for the 'A' series railcars, and ask: (a) does the contract provide for penalties to be applied when a railcar breaks down; (b) if yes to (a), what are the circumstances when penalties can be applied; (c) on how many occasions were penalties applied in: (i) 2011; (ii) 2012; and (iii) 2013; (d) on each occasion in (c): (i) what was the reason for the penalty; and (ii) what was the penalty amount; (e) on how many occasions in each year did a train break down with no penalty applied in: (i) 2011; (ii) 2012; and (iii) 2013; and (f) for each case in (e), why was no penalty applied?

AnswerView source ↗

Answered
24 June 2014
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
49 days
(a) Yes.
(b) Penalties can be applied when a service:
· Is cancelled or short- due to a technical fault of a railcar.
· Incurs a delay greater than or equal to four minutes due to a technical fault of a railcar.
(c)(i)-(ii) Nil.
(iii) 244 Lost Time Incidents and 94 Train Cancellation penalties were applied.
(d)(i) See part (c)(iii).
(ii) Lost Time Incidents attracted a total penalty amount of $41 028.00 and Train Cancellations attracted a total penalty amount of $310 291.00.
(e)(i)-(f) The Public Transport Authority advises that significant resources would need to be diverted from essential operational duties in order to answer this question.