Mr. Day questions the Education and Training portfolio regarding funds allocated to Lesmurdie Primary School from the $65 million school maintenance program between 2004-2007, and the purposes for which these funds were/will be used. The answer details specific maintenance and refurbishment projects undertaken at the school.

AnsweredQoN 670Legislative Assembly
Asked
28 March 2006
Portfolio
Education and Training

QuestionView source ↗

With reference to Lesmurdie Primary School, I ask -
(1) How much funds have been spent or have been allocated from the $65 million school maintenance program in 2004-2005, 2005-2006 and 2006-2007?
(2) For which purposes have or will the funds be expended and when?

AnswerView source ↗

Answered
6 April 2006
Response time
9 days
2. Works funded from the Fixing our Schools allocation at Lesmurdie Primary School include: Investigation of junior block roof issues. Removal of tree stumps from play area. Resurface of netball court. Repairs to dental therapy concrete ramp. Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Investigation of junior block roof issues. Removal of tree stumps from play area. Resurface of netball court. Repairs to dental therapy concrete ramp. Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Removal of tree stumps from play area. Resurface of netball court. Repairs to dental therapy concrete ramp. Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Resurface of netball court. Repairs to dental therapy concrete ramp. Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Repairs to dental therapy concrete ramp. Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Re-roof to toilet block, middle block, senior block, verandahs and links (to eliminate box gutters). Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Replace bag hooks. Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Replace vinyl tiles to junior block. Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Replace link mesh fence between covered assembly area and toilet block. Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Other works to be completed by June 2006 include: Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Toilet block refurbishment. Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Refresh non-slip finish to path from road to administration. Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Rectify gutter over junior block doors. Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Repair scotias to covered assembly ceiling. Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Provide "EXIT" signage where necessary. Replace six gas heaters. Painting.
Replace six gas heaters. Painting.
Painting.