❓ Hon Peter Collier asks about the land-based formwork and construction progress of the Matagarup Bridge by York Rizzani joint venture at the time of the supply agreement termination. The Minister provides information on the completion of the concrete piers.
AnsweredQoN 619Legislative Council
QuestionView source ↗
OPTUS STADIUM — MATAGARUP BRIDGE
619. Hon PETER COLLIER to
the minister representing the Minister for Transport:
I refer to the supply agreement
between York Rizzani and the Bianco Engineering Services–Toyota Tsusho
joint venture to manufacture the bridge decking and design features of the
pedestrian footbridge to Optus Stadium.
(1) Which company
was contracted to undertake the land-based formwork and construction for the
bridge?
(2) At the time
of the termination of the supply agreement, how much of the land-based formwork
and construction had been completed?
619. Hon PETER COLLIER to
the minister representing the Minister for Transport:
I refer to the supply agreement
between York Rizzani and the Bianco Engineering Services–Toyota Tsusho
joint venture to manufacture the bridge decking and design features of the
pedestrian footbridge to Optus Stadium.
(1) Which company
was contracted to undertake the land-based formwork and construction for the
bridge?
(2) At the time
of the termination of the supply agreement, how much of the land-based formwork
and construction had been completed?
AnswerView source ↗
I thank the honourable Leader of the
Opposition for some notice of the question. Although it is unclear what the
member is referring to by the term ''land-based formwork'', and
given Main Roads' interpretation of the question, the answer is as
follows.
(1) The concrete
piers that form the substructure of the bridge and support the arches were
completed by the York Rizzani joint venture.
(2) At the time of termination,
these piers were complete.
Opposition for some notice of the question. Although it is unclear what the
member is referring to by the term ''land-based formwork'', and
given Main Roads' interpretation of the question, the answer is as
follows.
(1) The concrete
piers that form the substructure of the bridge and support the arches were
completed by the York Rizzani joint venture.
(2) At the time of termination,
these piers were complete.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.