❓ Hon Martin Pritchard asks about the status and expenditure of Stage 1 of the Hamilton Precinct project, specifically regarding delays and costs. The Minister clarifies the scope of the delayed component and provides expenditure figures.
AnsweredQoN 602Legislative Council
QuestionView source ↗
HOUSING AUTHORITY — HAMILTON PRECINCT
PROJECT — STAGE 1
602. Hon MARTIN PRITCHARD to the Minister
for Housing:
I refer to the recent Estimates
Committee B hearing in the other place on the Housing Authority and
supplementary information B61 on stage 1 of the Hamilton Precinct project.
(1) Does the
project alternatively described as ''deferred until 2020–21''
and ''put on hold pending an upturn in demand'' refer to the
entire Hamilton Precinct stage 1 development?
(2) If no to (1), what is the
project that is referred to?
(3) If yes to
(1), is the project's current status ''deferred until 2020–21''
or ''put on hold pending an upturn in demand''?
(4) What is the
total amount expended by government on the precinct, including legal services,
development and project management costs, infrastructure, civil works and
engineer design work?
PROJECT — STAGE 1
602. Hon MARTIN PRITCHARD to the Minister
for Housing:
I refer to the recent Estimates
Committee B hearing in the other place on the Housing Authority and
supplementary information B61 on stage 1 of the Hamilton Precinct project.
(1) Does the
project alternatively described as ''deferred until 2020–21''
and ''put on hold pending an upturn in demand'' refer to the
entire Hamilton Precinct stage 1 development?
(2) If no to (1), what is the
project that is referred to?
(3) If yes to
(1), is the project's current status ''deferred until 2020–21''
or ''put on hold pending an upturn in demand''?
(4) What is the
total amount expended by government on the precinct, including legal services,
development and project management costs, infrastructure, civil works and
engineer design work?
AnswerView source ↗
On behalf of the Minister for
Housing, I thank the honourable member for some notice of the question.
The Housing Authority advises the
following —
(1)–(2) No.
Stage 1 is a 25-hectare component that was proposed to deliver 298 lots. The
project referred to, that was delayed to 2020–21, is the first
component of stage 1 that proposed to deliver 93 lots that will yield more than
100 dwellings.
(3) Not applicable.
(4) As at 31 May 2016,
the Housing Authority has paid $2 038 068.53 and is capitalised as part of the
asset.
Housing, I thank the honourable member for some notice of the question.
The Housing Authority advises the
following —
(1)–(2) No.
Stage 1 is a 25-hectare component that was proposed to deliver 298 lots. The
project referred to, that was delayed to 2020–21, is the first
component of stage 1 that proposed to deliver 93 lots that will yield more than
100 dwellings.
(3) Not applicable.
(4) As at 31 May 2016,
the Housing Authority has paid $2 038 068.53 and is capitalised as part of the
asset.
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.