Mr. Birney questions the Police Minister about budget allocations for the Goldfields-Esperance region and Kalgoorlie-Boulder Police Station, revealing discrepancies between requested, budgeted, and expended amounts, particularly regarding overtime and specific incidents.

AnsweredQoN 1739Legislative Assembly
Asked
12 August 2003
Portfolio
Police and Emergency Services

QuestionView source ↗

(1) Will the Minister advise the date that the first formal budget submission was submitted by the Goldfields-Esperance region to the Police Command relating to the 2003/2004 financial year?
(2) Will the Minister advise the total budget figure requested by the Goldfields-Esperance Police region on that occasion?
(3) Will the Minister advise the total budget figure requested by the Kalgoorlie–Boulder Police station for the 2003/2004 financial year?
(4) Will the Minister advise the final budget amount approved by Police Command for the Goldfields-Esperance region for the 2003/2004 financial year?
(5) Will the Minister advise the final budget amount approved by Police Command for the Kalgoorlie–Boulder Police station for the 2003/2004 financial year?
(6) Will the Minister explain the difference, if any, between the budget figure requested by the Goldfields-Esperance Police region and the final budget amount approved for that region by Police Command for the 2003/2004 financial year?
(7) Will the Minister explain the difference, if any, between the budget figure requested by the Kalgoorlie–Boulder Police station and the final budget amount approved for that station by the Police Command for the 2003/2004 financial year?
(8) Will the Minister advise the total amount requested, budgeted and actually expended in the Goldfields-Esperance Police region for the 1999/2000, 2000/2001, 2001/2002, and 2002/2003 financial years?
(9) Will the Minister advise the total amount requested, budgeted and actually expended by the Kalgoorlie-Boulder Police Station for the 1999/2000, 2000/2001, 2001/2002, and 2002/2003 financial years?
(10) Will the Minister explain any difference in the amount requested, the amount budgeted and the actual amount expended on policing in the Goldfields-Esperance region for the 1999/2000, 2000/2001, 2001/2002, and 2002/2003 financial years?
(11) Will the Minister explain any difference in the amount requested, the amount budgeted and the actual amount expended on policing by the Kalgoorlie-Boulder Police Station for the 1999/2000, 2000/2001, 2001/2002, and 2002/2003 financial years?

AnswerView source ↗

Answered
18 November 2003
Responded by
Minister for Police and Emergency Services
Response time
98 days
(2) $2,474,650. (3) The Police Service advise that they do not provide details of budget allocations to sub-districts. They advise that it is the responsibility of the District Superintendent to manage their funds and to assign appropriate resources to deliver an overall policing service within that District. In this regard, the allocations to the sub-districts may vary throughout the financial year to ensure the provision of an overall service by the District. (4) $2,593,510 (5) Refer to part (3). (6) The additional funding was provided to cater for an increase for back to back patrols as part of the Gordon Inquiry recommendations and funding for the Warburton Police Post. (7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(3) The Police Service advise that they do not provide details of budget allocations to sub-districts. They advise that it is the responsibility of the District Superintendent to manage their funds and to assign appropriate resources to deliver an overall policing service within that District. In this regard, the allocations to the sub-districts may vary throughout the financial year to ensure the provision of an overall service by the District. (4) $2,593,510 (5) Refer to part (3). (6) The additional funding was provided to cater for an increase for back to back patrols as part of the Gordon Inquiry recommendations and funding for the Warburton Police Post. (7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(4) $2,593,510 (5) Refer to part (3). (6) The additional funding was provided to cater for an increase for back to back patrols as part of the Gordon Inquiry recommendations and funding for the Warburton Police Post. (7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(5) Refer to part (3). (6) The additional funding was provided to cater for an increase for back to back patrols as part of the Gordon Inquiry recommendations and funding for the Warburton Police Post. (7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(6) The additional funding was provided to cater for an increase for back to back patrols as part of the Gordon Inquiry recommendations and funding for the Warburton Police Post. (7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(7) Refer to part (3). (8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(8) 1999/2000 Requested $2,770,500 Budgeted $2,770,500 Expended $2,796,528 N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
N.B. The Police Service advise that in 1999/2000 what is now known as the Goldfields-Esperance District did not exist in that form. In configuring the Goldfields-Esperance District a number of stations were added to the Goldfields-Esperance District and a number were transferred to the Mid West Gascoyne District. 2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2000/2001 Requested $2,253,700 Budgeted $2,297,560 Expended $2,366,673 2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2001/2002 Reqeusted $2,372,630 Budgeted $2,445,170 Expended $2,548,742 2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2002/2003 Requested $2,401,180 Budgeted $2,436,650 Expended $2,484,298 (9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(9) See part (3). (10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(10) The Police Service advise: 1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
1999/2000 Higher overtime costs than planned. 2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2000/2001 Cost of Major Incident – Operation Sandlewood (Orabanda Hotel bombing) resulted in additional costs being incurred. 2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2001/2002 Cost providing isolated patrols to Warburton and Warakurna and surrounding communities were greater than anticipated. 2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2002/2003 Higher than anticipated vehicle operating costs. (11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
(11) See part (3), however in addition I am able to advise that in 2001/2002 and 2002/2003 the Kalgoorlie Police Station did expend and receive more funding than was allocated for the following reasons. 2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2001/2002 Higher than anticipated overtime, travel and vehicle operating expenses. 2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
2002/2003 Higher than anticipated shift and vehicle operating expenses. I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.
I am unable to advise whether the Kalgoorlie Police Station expended more than was allocated to it in 1999/2000 and 2000/2001 and the reason for any variation, if any, as the Police Service advise that the amounts requested, budgeted, and expended for the Station are unavailable.

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more