The WA parliamentary question seeks details on the reassignment of the Roe 8 Alliance workforce following the project's cancellation. The answer provides figures on reassignments to various projects and the timeline for these reallocations.

AnsweredQoN 599Legislative Assembly
Asked
25 May 2017
Portfolio
Transport

QuestionView source ↗

I refer to the State Government’s announcement on 10 May 2017 in relation to Roe 8, and ask: (a) how many of the 231 Roe 8 Alliance workforce have been reassigned to new projects: (i) what is the total for each project; and (ii) when were they reallocated to each project; and (b) how many of the Roe 8 Alliance workforce are currently still assigned to the Roe 8 project?

AnswerView source ↗

Answered
27 June 2017
Responded by
Minister for Transport
Response time
7 days
(a) 133. A further 88 Design and Construction staff were redeployed to other projects within their parent companies’ business portfolios. Remaining personnel were associated with site security, providing casual support to police during construction.
(i) Roe 8 Site Rehabilitation: 33
Murdoch Drive Connection: 30
Armadale Road Upgrade, Anstey Road to Tapper Road: 28
Wanneroo Road Upgrade, Joondalup Drive to Flynn Drive: 21
Project management and administration staff (for all projects): 21
(ii) Re-allocation commenced from 3 April 2017 as part of the initial contract renegotiations.
(b) There is no Roe 8 project, however 33 members of the Roe 8 Alliance workforce have been assigned to the Roe 8 site rehabilitation.