Mr. Kelly questions the Water Corporation about rescheduled regional water projects and associated cost savings, capacity delays, and revised completion timelines. The Water Corporation responds that the figures are indicative and subject to change due to various factors.

AnsweredQoN 3272Legislative Assembly
Asked
27 November 2014
Portfolio
Water

QuestionView source ↗

I refer to page 18 of the Water Corporation’s Strategic Development Plan 2014/15 to 2018/19 , and I ask: (a) which regional water growth (major schemes) projects have been rescheduled as part of the $79 million saving measures; (b) in each case what capacity has been delayed and what was the cost of each upgrade; (c) in each case, what was the original timeline for completion; (d) in each case, what are the new completion dates due to the delay; and (e) which schemes are currently considered to be the highest risk?

AnswerView source ↗

Answered
24 February 2015
Responded by
Minister for Water
Response time
89 days
The figures outlined on page 18 of the Strategic Development Plan are indicative and used for planning purposes only.
The Water Corporation's capital investment program is regularly reprioritised due to changing consumption patterns, population growth and unforeseen circumstances.