Question regarding the relocation of a water treatment plant and its timing, specifically in relation to the drilling of new bores. The answer provides details on the planned location and estimated timeframe for the move.

AnsweredQoN 1286Legislative Assembly
Asked
27 November 2001
Member
Portfolio
Government Enterprises

QuestionView source ↗

(b) exactly where will the treatment plant be moved to and when is this move expected to occur?
(b) Movement of treatment plant is planned to Lot A4293P around 2012 (at the same time as the 2nd new bore is drilled)

AnswerView source ↗

Answered
6 December 2001
Responded by
Minister representing the Minister for Government Enterprises
Response time
9 days
(a) New elevated tank in 2002 at current site (Periwinkle Place
New ground tank in 2002 at current site (Periwinkle Place)
Timing for new bores is unknown at present and the Water Corporation is undertaking tests of the existing bores to better determine when. Tentative dates are 2002 for the 1st new bore and 2012 for the 2nd new bore.
Location of new bores is planned for Lot A4293P at the end of the closed-off section of Hayfield Drive.
(b) Movement of treatment plant is planned to Lot A4293P around 2012 (at the same time as the 2nd new bore is drilled)