Question regarding funding allocated to and progress of works on the Nungarin-Merredin Road, part of the grain freight network. The parliamentary secretary provides details on funding, expenditure, works completed, and timeframe for completion.

AnsweredQoN 800Legislative Council
Asked
19 November 2013
Portfolio
Transport

QuestionView source ↗

GRAIN
FREIGHT NETWORK
800. Hon KEN TRAVERS to the parliamentary
secretary representing the Minister for Transport:
I refer to the grain freight
network.
(1) What is the
total amount of funding allocated for works on the Nungarin–Merredin
Road?
(2) How much of
this funding has been spent to date?
(3) What works
will be completed with this expenditure?
(4) What is the
time frame to complete the works on this road?

AnswerView source ↗

I thank the honourable member for
some notice of this question.
(1) The total amount is $5.218 million.
(2) Sixty-two per cent.
(3) Thirty-seven
kilometres of widening of the seal to eight metres.
(4) The time frame for completion is 2014–15.