In 2015-16, what road improvements were completed in the South West region?

AnswerView source ↗

Answered
28 June 2016
Responded by
Parliamentary Secretary representing the Minister for Transport
Response time
61 days
The following Improvements were made on State Roads in the South West Region in 2015/16:
Bannister Marradong Road
widened intersection and widened the adjacent road with sealed shoulders.
Bussell Highway
Caves Road
Widening to provide sealed shoulders.
Coalfields Highway
Realigned highway with sealed shoulders and a wide centre median including upgrading intersection and upgrade of the truck bay A further partially completed realignment will be completed in late 2016 when weather conditions improve.
Donnybrook Kojonup Road
Forrest Highway
Installed street lighting at intersection.
South Western Highway
Vasse Highway
Widening with sealed shoulders.