❓ A parliamentary question regarding the progress, timelines, planning, and funding of upgrades to Loch and Grant Street train stations. The Minister provides specific details on work completed, expected completion dates, planning commencement, and funding allocation.
AnsweredQoN 705Legislative Council
QuestionView source ↗
I refer to parliamentary question No.206, regarding extensions to the Loch and Grant Street train stations, and ask -
(1) When did work commence and what is the nature of the 15 percent of work to Loch Street and five percent of work to Grant Street that has been completed?
(2) When is it expected that construction will be complete?
(3) When was planning for these upgrades commenced?
(4) When was funding allocated?
(1) When did work commence and what is the nature of the 15 percent of work to Loch Street and five percent of work to Grant Street that has been completed?
(2) When is it expected that construction will be complete?
(3) When was planning for these upgrades commenced?
(4) When was funding allocated?
AnswerView source ↗
Answered
2 June 2009
Responded by
Minister for Transport
Response time
28 days
I trust that the Honourable Member was refering to Legislative Council Question On Notice No 253.
(1) Work commenced in February 2009. The nature of the 15 per cent work completed at Loch Street station was the boring of holes for the platform face posts plus all the overhead works. The nature of the 5 per cent work completed at Grant Street station was all the overhead works.
(2) Lock Street was completed in April 2009. Grant Street is expected to be completed by May 2009.
(3) The first quarter of 2008.
(4) July 2008.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
(1) Work commenced in February 2009. The nature of the 15 per cent work completed at Loch Street station was the boring of holes for the platform face posts plus all the overhead works. The nature of the 5 per cent work completed at Grant Street station was all the overhead works.
(2) Lock Street was completed in April 2009. Grant Street is expected to be completed by May 2009.
(3) The first quarter of 2008.
(4) July 2008.
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com
Explore WA Government Data
Search the full archive in the free dashboard, or query programmatically via API.
Explore more
Government Gazette
Appointments, regulatory notices, planning changes.
Hansard
Debates, questions, speeches and sentiment.
Tabled Papers
Reports and documents tabled in Parliament.
Committees
Committee profiles and recent reports.
Regulations
Subsidiary legislation with filters and summaries.
Bills
Proposed laws and parliamentary progress.
Acts
Current WA legislation and summaries.
Explanatory Memoranda
Bills with EMs (text/PDF) available.
Members
MP profiles, party breakdown and rankings.
Pollie Rankings
Data-driven rankings across 19 categories.
Amendment Chains
Track how schemes and regulations evolve over time.