Mr McGowan questions the funding and timeline of Stage 3 of the Collie CBD Revitalisation Plan, a priority project in the Collie SuperTown Implementation Schedule. The answer details funding received and withdrawn, explains allocation based on milestones, and states the expected completion date.

AnsweredQoN 1818Legislative Assembly
Asked
18 February 2014
Portfolio
Regional Development

QuestionView source ↗

I refer to Stage 3 of the CBD Revitalisation Plan, listed as a priority project in the Collie SuperTown Implementation Schedule, and I ask: (a) how much funding has the project received for the financial years: (i) 2011-2012; and (ii) 2012-2013; (b) how much funding has been allocated for the project for the financial years: (i) 2013-2014; (ii) 2014-2015; and (iii) 2016-2017; and (c) what is the expected completion date for the project?

AnswerView source ↗

Answered
18 March 2014
Responded by
Minister for Regional Development
Response time
28 days
(a) $11 010 000 was deposited into the relevant Shire account for the Collie CBD Revitalisation project.
(i)  No funding was withdrawn in 2011-12.
(ii) $2 500 000 was withdrawn in 2012-13.
(b) Funds are allocated according to project milestones, not financial  years.
(i)-(iii)  Not applicable. Milestones have not yet been met by the Shire of Collie  for further funds to be withdrawn.
(c) The project completion date, as stated in the Financial Assistance Agreement, is December 2014.