Hon Simon O'Brien asks about provisions for outstanding contractor claims related to the Mandurah railway project. Hon Adele Farina responds, stating the project's estimated cost and that Leighton Contractors has initiated litigation, with additional funding to be considered upon finalisation of claims.

AnsweredQoN 167Legislative Council
Asked
12 March 2008
Portfolio
Planning and Infrastructure

QuestionView source ↗

SOUTHERN SUBURBS RAILWAY — CONTRACTOR CLAIMS
(1) What provision has been made, or will be made, in the forward estimates for outstanding claims against the state by contractors involved in the Mandurah railway project? (2) Who are the claimants? Hon ADELE FARINA

AnswerView source ↗

I thank the member for some notice of this question. (1)-(2) Currently the estimated total cost, which was reflected in the Government Mid-year Financial Projections Statement , for the New MetroRail project is $1.664 billion. A number of claims remained outstanding, including some that are subject to litigation. Leighton Contractors is the only contractor to have initiated litigation. If required, additional funding will be considered as and when claims and litigation are finalised.
(2) Who are the claimants? Hon ADELE FARINA replied: I thank the member for some notice of this question. (1)-(2) Currently the estimated total cost, which was reflected in the Government Mid-year Financial Projections Statement , for the New MetroRail project is $1.664 billion. A number of claims remained outstanding, including some that are subject to litigation. Leighton Contractors is the only contractor to have initiated litigation. If required, additional funding will be considered as and when claims and litigation are finalised.
Hon ADELE FARINA replied: I thank the member for some notice of this question. (1)-(2) Currently the estimated total cost, which was reflected in the Government Mid-year Financial Projections Statement , for the New MetroRail project is $1.664 billion. A number of claims remained outstanding, including some that are subject to litigation. Leighton Contractors is the only contractor to have initiated litigation. If required, additional funding will be considered as and when claims and litigation are finalised.
I thank the member for some notice of this question. (1)-(2) Currently the estimated total cost, which was reflected in the Government Mid-year Financial Projections Statement , for the New MetroRail project is $1.664 billion. A number of claims remained outstanding, including some that are subject to litigation. Leighton Contractors is the only contractor to have initiated litigation. If required, additional funding will be considered as and when claims and litigation are finalised.
(1)-(2) Currently the estimated total cost, which was reflected in the Government Mid-year Financial Projections Statement , for the New MetroRail project is $1.664 billion. A number of claims remained outstanding, including some that are subject to litigation. Leighton Contractors is the only contractor to have initiated litigation. If required, additional funding will be considered as and when claims and litigation are finalised.