Question regarding the progress and delays of the Abernethy Road rail crossing works in Byford, specifically seeking explanations for missed deadlines and the expected completion date. The answer redirects responsibility to the Shire of Serpentine-Jarrahdale.

AnsweredQoN 6392Legislative Assembly
Asked
8 September 2020
Portfolio
Transport; Planning

QuestionView source ↗

I refer to the Abernethy Road rail crossing works in Byford, and I ask: (a) Will you please provide an update regarding the progress of these works; (b) Can you please explain why the works were delayed and were not completed by the Shire of Serpentine Jarrahdale's original timeframe of February, or their updated timeframe of July; and (c) What is the expected completion date for these works?

AnswerView source ↗

Answered
8 October 2020
Responded by
Minister for Transport; Planning
Response time
9 days
(a) - (c)  The road upgrade project is being undertaken by the Shire of Serpentine-Jarrahdale.