With reference to the Minister’s 26 January 2012 media statement about the air cooling program for schools, I ask:
(a) which schools are intended to have air cooling by 1 March?
(b) which schools will be completed by 1 April 2012?
(c) which schools will be completed by 1 May 2012?
(d) when will the remainder of schools be completed and which schools are they?

AnswerView source ↗

Answered
20 March 2012
Responded by
Minister for Education
Response time
28 days
(a)-(c) The air-cooling program is being delivered in a number of contract packages. The attached paper lists public schools in each package and the contractual completion date for each package. Schools will be progressively completed within this timeframe.
(d) Consistent with the Government's commitment, made in May 2011, to air cool all public schools, at a cost of $52 million, over four years, all remaining schools will be progressively air cooled by the end of 2015.
[see tabled paper no]
Notice: This document is created or edited using unregistered or evaluation copy of rtLib valid for testing or development purposes only. To use it for productive or any other purposes please register it. You may purchase the license on
http://www.rtlib.com

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more