(1) What additional capital works have been completed at Kaleeya Hospital between its purchase in early 2005 and 31 December 2005?
(2) What has been the cost of each of these capital works?
(3) Were these capital works budgeted for in the previous annual budget and if so, how much was budgeted?

AnswerView source ↗

Answered
2 May 2006
Responded by
Parliamentary Secretary representing the Minister for Health
Response time
42 days
Building Works $161,119 Furniture and Fittings $20,997 Plant and Machinery $24,733 (3) No.
(3) No.